Construction Update September 2017

The finishing touches are being completed on the building and furniture has now started to be delivered and setup. All resident rooms, sitting areas, parlors, and waiting areas have been furnished. The window treatments are next to adorned, office furniture to be setup, and artwork to be displayed throughout the building. We are looking ahead to opening day and welcoming our first residents.

2017-09-14 10.57.53-1.jpg

Construction Update - 11/2

Parapet framing has been completed.  The roof installation is underway and Wing A & B will be watertight by the end of next week.  The masonry has started in the courtyard and vinyl trim has started around the windows.  Excavation for the new storm water management system is continuing on the west side of the Addition.

Construction Update 10/14

Parapet framing continuing around to B wing. Majority of the new windows are in place at the addition. The slab on grade has been poured at B wing as well, with the prep work for the slab on grade pour at A wing being coordinated. The roof materials at B wing have been delivered and construction of the roof at B wing has commenced. Steel joists are all in place with the only remaining decking to be laid at the high canopy at the new main entry.

Construction Update - 10/4

With the exterior sheathing in place, taping of the joints has commenced as well as installation of the new windows on the first level. Metal decking is being laid out and fastened to the joists at A wing. Parapet framing is occurring at B wing and starting to shape what the elevation will eventually look like at the addition. 

Construction Update - 9/27

The joists and structural steel are 85% in place, as spreading of the joists at A and I wing continue. Sheathing around the second level exterior wall of the addition is nearing completion.  Metal decking at the B wing roof has been started and laid out. Light pole bases are continuing to be set around the site. 

Construction Update - 9/22

Construction is continuing as the summer draws to a close.

Structural Steel and Joists continue to be set, detailed and welded into place. The crane has moved from the center courtyard at the addition to the main entry circle, to better reach and erect the canopy steel and joists at what will be the future main entry for the Delhi Rehabilitation & Nursing Center. Along the 2nd level exterior walls the ZIP system is being fastened into place as well.

Construction Update - 8/31

Construction is continuing - with the second floor nearly completed on the new addition, landscaping improving, and rehabilitation of the existing building beginning.

Construction Update - 8/25

Construction is coming along well! The second level is taking shape, and landscaping of the grounds has begun in earnest.