Construction Update - 10/4

With the exterior sheathing in place, taping of the joints has commenced as well as installation of the new windows on the first level. Metal decking is being laid out and fastened to the joists at A wing. Parapet framing is occurring at B wing and starting to shape what the elevation will eventually look like at the addition.