Construction Update 10/14

Parapet framing continuing around to B wing. Majority of the new windows are in place at the addition. The slab on grade has been poured at B wing as well, with the prep work for the slab on grade pour at A wing being coordinated. The roof materials at B wing have been delivered and construction of the roof at B wing has commenced. Steel joists are all in place with the only remaining decking to be laid at the high canopy at the new main entry.