Construction Update - 9/27

The joists and structural steel are 85% in place, as spreading of the joists at A and I wing continue. Sheathing around the second level exterior wall of the addition is nearing completion.  Metal decking at the B wing roof has been started and laid out. Light pole bases are continuing to be set around the site.